Boeing shares fell about 10% on October 27 after the company said it will miss its 2026 target of 500 737 deliveries. The drop was the stock’s largest since April 3, 2025, a span of 18 months. Cash in the quarter beat forecasts, and the last two 737 MAX models had just cleared the FAA.

CEO Kelly Ortberg told investors that progress is not always linear and that he is still “on the right track.” The tape treated a factory that cannot yet hold 47 jets a month as the only number that priced, because that gap just moved the cash recovery Wall Street had already put in its models.

Shares Fall About 10% After the 737 Miss

The print itself was not a collapse. Revenue rose 4% to $24.2 billion. Operating cash flow was $1.5 billion, up 33% from a year earlier. Free cash flow came in at $464 million, above a $325.1 million estimate, even after about $700 million in Department of Justice settlement payments.

THE QUARTER IN FOUR FIGURES

  • The stock: About 10% lower on October 27, the largest decline since April 3, 2025.
  • Core loss: 34 cents a share, against a 21-cent loss that analysts had modeled and a $7.47 loss a year earlier.
  • Cash: $464 million of free cash flow, versus $238 million a year earlier.
  • Backlog: A record $745 billion, including more than 6,300 commercial airplanes.

The third-quarter results filed with the SEC show a GAAP net loss of $116 million, against a $5.34 billion loss a year earlier that carried a 777X charge. Operating earnings were $354 million. A $252 million gain on the sale of HRL Laboratories made up most of that figure.

Boeing posted the release the same morning and pointed investors to the call.

Jay Malave, the chief financial officer, said the delay in holding 47 737s a month “is expected to translate to the lower delivery output and come in shy of the 500 delivery target.” That sentence did more damage than the 34-cent loss.

A Rate of 47 That Will Not Hold Until 2027

Boeing handed over 161 commercial airplanes in the quarter, one more than a year earlier, and 475 in the first nine months, up 8% from 440. The 737 did the heavy lifting, and it still was not enough.

COMMERCIAL DELIVERIES THROUGH SEPTEMBER

Program Q3 2026 First 9 months
737 124 367
767 10 26
777 5 20
787 Dreamliner 22 62
Total 161 475

Company delivery totals list 124 737s in the third quarter and 367 through September. Hitting 500 would have required 133 more in the fourth quarter. The nine-month pace is about 41 a month.

Ortberg had already warned in September that wing output was the brake. On the October 27 call he made the slip official.

It is taking us longer than we had expected to demonstrate performance at rate 47. We’re making progress, but we still have more work to do, and I’m expecting it’ll take us into next year to get fully stable at this rate.

Kelly Ortberg, Boeing CEO, on the third-quarter earnings call

As recently as May, executives still talked about 47 a month in the summer of 2026. The next step, 52 a month, is now set for the second half of 2027. Final assembly has cut rework 40% since the start of last year, Ortberg said. The constraint sits earlier in the line.

WHAT IS STILL PACING THE 737 LINE

  • Wings: Output is improving, Ortberg said, but it has not yet held the level needed to prove 47 a month.
  • Wichita fuselages: Boeing took back the former Spirit AeroSystems plant in December 2025 and still has to lift fuselage output in step with Renton.
  • Everett’s North Line: A fourth 737 line opened in July; rate 52 depends on that line adding volume, not only on the three lines in Renton.
  • 787 seats and engines: The Dreamliner is stable at eight a month, with a move to 10 by year-end, and full-year deliveries are tracking the lower end of a 90 to 100 range.

THE 737 RATE SINCE THE FAA CAP

  1. January 2024: The FAA caps 737 output at 38 a month after a door plug blows off an Alaska Airlines 737 MAX 9.
  2. December 2025: Boeing closes its purchase of Spirit AeroSystems’ commercial work, including 737 fuselages in Wichita.
  3. July 2026: A new 737 line opens in Everett, the first outside Renton.
  4. October 20, 2026: The FAA certifies the 737-10, completing the MAX family.
  5. October 27, 2026: Ortberg says 47 a month will not be stable until 2027, and Malave says 500 737 deliveries are out of reach.

The sequence is the argument. Boeing spent two years getting the regulator to let it run faster, then spent 2026 unable to prove the next rate.

The FAA Finished the MAX Family Last Week

On October 20, a week before the call, the FAA issued certification for the 737 MAX-10 and updated the production limitation record so Boeing can build it. The 737-7 had already received amended type certification during the third quarter. Those were the last two MAX variants without a U.S. certificate.

U.S. Transportation Secretary Sean Duffy handed over the papers in Everett.

This is a major win for American manufacturing and our nation’s status as a global aviation powerhouse.

Sean Duffy, U.S. Transportation Secretary, at the October 20 certification

Stephanie Pope, president of Boeing Commercial Airplanes, said the development team certified the 737-7 and then finished the 737-10 tests without losing the thread. The largest MAX is more than 30 percent of the MAX order book, with 1,555 orders from more than 30 customers. Customers have ordered 7,350 MAX family jets, and Boeing had delivered nearly 2,500 as of September.

The test program logged nearly 1,000 flights. The airplane also carries an enhanced angle-of-attack system that will become standard on new MAX production. None of that changed the 47-a-month math, because a certificate is not a wing, a fuselage, or a finished jet at the delivery gate.

$3 Billion of Free Cash in 2027

The delivery miss is how investors got to the cash slide. Boeing’s own deck now shows about $2 billion of free cash in 2026, then about $3 billion in 2027, $6 billion in 2028, and a $10 billion target in 2029. Malave said 2027 includes extra capital spending to support growth and recent awards, including the Navy fighter work.

BOEING’S FREE CASH FLOW PATH

Year Operating cash flow Capital spending Free cash flow
2026 About $6B About $4B About $2B
2027 About $8B About $5B About $3B
2028 About $10B About $4B About $6B
2029 About $14B About $4B About $10B

LSEG consensus had been $5.6 billion in 2027 and $9.6 billion in 2028. That is $2.6 billion less cash next year than the Street had on the sheet, and $3.6 billion less the year after. The $10 billion mark, which many models had in 2028, now sits in 2029 and assumes 737 rates of 52 to 58 a month and 12 787s a month.

Nine-month free cash flow is still negative $359 million. The company ended the quarter with $20.7 billion in cash and marketable securities and $45.9 billion of debt, with $10 billion of credit lines undrawn. Liquidity is not the panic. The ramp is.

Kenneth Herbert at RBC kept an Outperform rating and a $235 target and said the debate is the drivers of free-cash-flow growth in 2027 and 2028. Sheila Kahyaoglu at Jefferies kept a Buy and a $265 target. Seth Seifman at JPMorgan stayed Overweight with a $290 target and still called out commercial costs.

Why Commercial Airplanes Still Lost $697 Million

Boeing Commercial Airplanes took in $10.72 billion in the quarter, down 3%, and posted an operating loss of $697 million. Analysts had modeled a loss closer to $361 million. The margin was minus 6.5%, versus minus 48.3% a year earlier, when the 777X charge hit.

The company said the quarter reflected a weaker delivery mix, higher projected costs tied to future rate changes, and higher estimated supply-chain costs. For the first nine months the commercial unit has lost $1.58 billion on $31.67 billion of revenue. Seifman said losses on a unit-accounting basis have stayed around $1.3 billion for five straight quarters, which is a different ledger than the operating line and a colder read on whether the line is actually earning money yet.

Management still talks about commercial deliveries rising more than 10% next year and the commercial margin reaching breakeven in early 2028. Those dates only work if 47 a month is real, then 52. Ortberg said 777X first delivery remains in 2027, with the line running about one airplane a month, and that current cost estimates can absorb a certification slip into mid-2027.

Airlines that planned capacity on MAX-7 and MAX-10 arrivals now have certificates and still do not have a factory that will feed them at the old pace. Lessors and carriers sitting on 737 MAX orders are the ones who feel a missed 500, not the people trading the stock for an afternoon.

Airbus Led Boeing by 72 Jets Through September

Defense and services paid the bills while the 737 line argued with its own calendar. Defense, Space and Security revenue rose 15% to $7.94 billion, with operating earnings of $492 million, including the HRL sale. The U.S. Navy selected Boeing to design and build the F/A-XX carrier fighter; that award is not yet in backlog, pending the rest of the source-selection process. Defense backlog is a record $101 billion. Global Services revenue was $5.57 billion, up 4%, with earnings of $1.02 billion and an 18.3% margin.

Commercial still sets the equity story. Airbus had delivered 547 aircraft through September, 72 more than Boeing’s 475. Boeing booked 300 net commercial orders in the quarter, including Turkish Airlines, Ethiopian Airlines and Lufthansa, and commercial backlog is a record $612 billion. Demand is not the hole. Output is.

Jim Cramer wrote that “Boeing got the kitchen sink today and people don’t see that.” A kitchen-sink quarter that arrives every time the company tries to raise rate stops looking like a cleanup. It starts looking like the way the line actually runs: certificates land, defense wins land, cash has a good quarter, and the 737 still cannot hold the number management put on the slide in the spring.

Ortberg’s Bet on a Slow 737 Ramp

Ortberg, who took the job after the quality crisis, is not selling speed. He is selling a line that does not break when it accelerates. That is a hard pitch on a day when 500 is gone and 47 has moved into 2027, because the last crisis was born in a factory that raised rate before the work was stable.

In a memo to staff he wrote that expectations are rising, “and they should,” and that Boeing has a stronger foundation than a year ago, with more work still required on the backlog, the culture, and daily execution. On the call he said the same thing in fewer words: progress will not be perfectly linear, and he is confident the company is on the right track.

Boeing still plans 52 737s a month in the second half of 2027. That date is now the one the $3 billion, the $6 billion, and the $10 billion have to clear.

Disclaimer: This article is news reporting and analysis of Boeing’s third-quarter 2026 results and share-price move, and it is for information only. It is not investment advice, a recommendation to buy or sell Boeing stock or any other security, or a forecast of future returns. Readers should consult a licensed financial adviser or broker before making any investment decision based on earnings figures, delivery targets, or cash-flow guidance. Share prices, production rates, and the free-cash-flow path cited here reflect company filings and market data from the October 27, 2026 session and can change.

Harry is the editor of BROAD BROWSE, which he owns, runs and largely writes himself as an independent publication. The site is deliberately wide, and keeping ten sections accurate with one editor depends on a rule he has followed through a decade in journalism, from reporter to editor: every section has its own primary record, and the article starts there. For business that means the filing and the earnings call transcript, for science the paper and its underlying data, for sports the official result, for auto and technology the product in his hands, for news the statement or the court document. Entertainment, lifestyle, travel and gaming get the same treatment, with the release, the itinerary or the game itself checked before writing begins. Readers come from many countries, so figures are given with context and checked before they are published. Corrections are made on the article with a dated note, and the site's corrections policy is public. He answers reader mail personally at support@broadbrowse.com.

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Trending